Constant tension speed mode Commissioning guide
Time:
2026-06-04 21:52

一、the Commissioning process

The following was an example of commwassioning the inverter in the speed mode:
Motor tuning tuning Remove the pulley between the motor and the reel of the winding part, set the nameplate parameters of the P group motor and perform the rotation self-tuning;
pay attention to the incorrect setting of the motor pole number, the system was not working properly.
Parameter initialization: Initialize the inverter to the winding inverter P0.01=5; then the inverter setting frequency shows 50.00Hz->0.00~0.50Hz
Control terminal wiring: AO1 was connected to the stretched AO output (note that the AO output function of the main unit was set to the operating frequency), and the AI2 was connected to the feedback signal of the pendulum.
Coarse part coarse adjustment PID: check P0.03=3; P0.04=1; P1.02=0 P1.05=2; acceleration/deceleration time P0.08, P0.09=1.0s; LED dwasplay AI1 should be 0, AI2 should be the swing position feedback voltage, manually swing the pendulum to record the highest position and the lowest position of the AI2 voltage, and find the voltage of the balance position, set P8.00 (default setting 5V); do not run the host only winding operation When the main engine was not running, swing the swing lever, and the running frequency of the inverter should change with the PID adjustment law.
Determine the basic parameter parameters of the winding part: H0.00=1; measure the winding diameter of the full roll and the empty winding diameter and set H0.07 and H0.08; the transmwassion ratio H0.06 was the motor speed and the pulley winding side shaft speed The ratio, the maximum line speed H0.04 was not the designed maximum line speed, but it must be determined what the line speed was when the front stage outputs 10V (maximum frequency).
Winding part of the winding volume operation Commissioning: determine that the current winding diameter H0.11 was conswastent with the actual empty winding diameter. The low speed starts the belt material run from the equilibrium position; it was estimated how many seconds each additional 0.1 mm was required from the empty roll to the full roll, and the value was set to the roll diameter refresh time H0.16.
Winding part of the full volume operation Commissioning: Replace the full volume, note that you need to manually change H1.11 to full volume, full volume start, adjust H0.01, H0.02, H0.03 according to pendulum performance.